Building Plan Permission (New/Additional/Revision/Reconstruction) - Less than 40,000 SQFT
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act
Total number of applications received
Total number of applications approved
Total number of applications Withdrawn/Returned/Rejected
Average time taken to obtain approval
Median time taken to obtain approval
Minimum time taken to obtain approval
Maximum time taken to obtain approval
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 0.00

Building Plan Permission (New/Additional/Revision/Reconstruction) - More than 40,000 SQFT
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act
Total number of applications received
Total number of applications approved
Total number of applications Withdrawn/Returned/Rejected
Average time taken to obtain approval
Median time taken to obtain approval
Minimum time taken to obtain approval
Maximum time taken to obtain approval
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 0.00

Building Plan Permission (New/Additional/Revision/Reconstruction) - High Rise Building
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act
Total number of applications received
Total number of applications approved
Total number of applications Withdrawn/Returned/Rejected
Average time taken to obtain approval
Median time taken to obtain approval
Minimum time taken to obtain approval
Maximum time taken to obtain approval
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 0.00

Plinth Inspection
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act
Total number of applications received
Total number of applications approved
Total number of applications Withdrawn/Returned/Rejected
Average time taken to obtain approval
Median time taken to obtain approval
Minimum time taken to obtain approval
Maximum time taken to obtain approval
Average fee taken by the Department for completion of entire process of obtaining approval/certificate No fee collected

Issue of Completion Certification
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act
Total number of applications received
Total number of applications approved
Total number of applications Withdrawn/Returned/Rejected
Average time taken to obtain approval
Median time taken to obtain approval
Minimum time taken to obtain approval
Maximum time taken to obtain approval
Average fee taken by the Department for completion of entire process of obtaining approval/certificate No fee collected
Change of Land Use Statistics FROM 01.01.2024 TO 28.02.2025
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 120 days
Total No.of application received 1097
No.of G.O issued 504
No.of application withdrawn/rejected/Returned 155
No.of application pending with applicant 128
No.of application sent to Govt. 83
No.of application in DO pending 105
No.of application in HO pending 122
Average time taken to obtain Government Order 212 days
Minimum time taken to obtain Government Order 84 days
Maximum time taken to obtain Government Order 339 days
Average fee taken by the Department for completion of entire process of obtaining Government Order Rs.20,000/-