Statistics
- Home
- Application Status
- Statistics
Updated: Daily
Last updated on: 29 December 2024 12:00 am
Last updated on: 29 December 2024 12:00 am
Statistics from 01/01/2024
Building Plan Permission (New/Additional/Revision/Reconstruction) - Less than 40,000 SQFT | |
---|---|
Particulars | Details |
Time limit prescribed as per the Public Service Guarantee Act | 45 |
Total number of applications received | 5040 |
Total number of applications approved | 1924 |
Total number of applications Withdrawn/Returned/Rejected | 2237 |
Average time taken to obtain approval | 1 mon 31 days |
Median time taken to obtain approval | 1 mon 22 days |
Minimum time taken to obtain approval | 3 days |
Maximum time taken to obtain approval | 11 mons 10 days |
Average fee taken by the Department for completion of entire process of obtaining approval/certificate | 907,150.00 |
Building Plan Permission (New/Additional/Revision/Reconstruction) - More than 40,000 SQFT | |
---|---|
Particulars | Details |
Time limit prescribed as per the Public Service Guarantee Act | 90 |
Total number of applications received | 1038 |
Total number of applications approved | 407 |
Total number of applications Withdrawn/Returned/Rejected | 247 |
Average time taken to obtain approval | 4 mons 19 days |
Median time taken to obtain approval | 4 mons 5 days |
Minimum time taken to obtain approval | 3 days |
Maximum time taken to obtain approval | 1 year 2 mons 23 days |
Average fee taken by the Department for completion of entire process of obtaining approval/certificate | 1,376,810.00 |
Building Plan Permission (New/Additional/Revision/Reconstruction) - High Rise Building | |
---|---|
Particulars | Details |
Time limit prescribed as per the Public Service Guarantee Act | 120 |
Total number of applications received | 147 |
Total number of applications approved | 39 |
Total number of applications Withdrawn/Returned/Rejected | 27 |
Average time taken to obtain approval | 5 mons 35 days |
Median time taken to obtain approval | 6 mons 11 days |
Minimum time taken to obtain approval | 11 days |
Maximum time taken to obtain approval | 1 year 1 mon 25 days |
Average fee taken by the Department for completion of entire process of obtaining approval/certificate | 31,105,318.00 |
Plinth Inspection | |
---|---|
Particulars | Details |
Time limit prescribed as per the Public Service Guarantee Act | 15 |
Total number of applications received | 248 |
Total number of applications approved | 124 |
Total number of applications Withdrawn/Returned/Rejected | 40 |
Average time taken to obtain approval | 1 mon 13 days |
Median time taken to obtain approval | 30 days |
Minimum time taken to obtain approval | 1 day |
Maximum time taken to obtain approval | 9 mons 28 days |
Average fee taken by the Department for completion of entire process of obtaining approval/certificate | No fee collected |
Issue of Completion Certification | |
---|---|
Particulars | Details |
Time limit prescribed as per the Public Service Guarantee Act | 30 |
Total number of applications received | 313 |
Total number of applications approved | 228 |
Total number of applications Withdrawn/Returned/Rejected | 45 |
Average time taken to obtain approval | 33 days |
Median time taken to obtain approval | 20 days |
Minimum time taken to obtain approval | 1 day |
Maximum time taken to obtain approval | 10 mons 3 days |
Average fee taken by the Department for completion of entire process of obtaining approval/certificate | No fee collected |
Change of Land Use Statistics FROM 01.01.2024 TO 30.11.2024 | |
---|---|
Particulars | Details |
Time limit prescribed as per the Public Service Guarantee Act | 120 days |
Total No.of application received | 982 |
No.of G.O issued | 402 |
No.of application withdrawn/rejected/Returned | 126 |
No.of application pending with applicant | 135 |
No.of application sent to Govt. | 88 |
No.of application in DO pending | 140 |
No.of application in HO pending | 91 |
Average time taken to obtain Government Order | 212 days |
Minimum time taken to obtain Government Order | 84 days |
Maximum time taken to obtain Government Order | 339 days |
Average fee taken by the Department for completion of entire process of obtaining Government Order | Rs.20,000/- |
Footer 1
Contact
- Second, Third and Fourth floor, E & C Market Road, Koyambedu, Chennai - 600 107.
- ctcptn@tn.gov.in
Footer Bottom
Copyright ©2024 The Department of Housing and Urban Development of state of Tamil Nadu