Statistics from 01/01/2024


Building Plan Permission (New/Additional/Revision/Reconstruction) - Less than 40,000 SQFT
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 45
Total number of applications received 5479
Total number of applications approved 2137
Total number of applications Withdrawn/Returned/Rejected 2495
Average time taken to obtain approval 1 mon 32 days
Median time taken to obtain approval 1 mon 22 days
Minimum time taken to obtain approval 3 days
Maximum time taken to obtain approval 1 year 5 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 901,730.00

Building Plan Permission (New/Additional/Revision/Reconstruction) - More than 40,000 SQFT
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 90
Total number of applications received 1123
Total number of applications approved 448
Total number of applications Withdrawn/Returned/Rejected 291
Average time taken to obtain approval 4 mons 20 days
Median time taken to obtain approval 4 mons 6 days
Minimum time taken to obtain approval 3 days
Maximum time taken to obtain approval 1 year 2 mons 23 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 1,444,131.00

Building Plan Permission (New/Additional/Revision/Reconstruction) - High Rise Building
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 120
Total number of applications received 160
Total number of applications approved 47
Total number of applications Withdrawn/Returned/Rejected 29
Average time taken to obtain approval 5 mons 40 days
Median time taken to obtain approval 6 mons 11 days
Minimum time taken to obtain approval 11 days
Maximum time taken to obtain approval 1 year 1 mon 25 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 29,821,997.00

Plinth Inspection
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 15
Total number of applications received 275
Total number of applications approved 132
Total number of applications Withdrawn/Returned/Rejected 45
Average time taken to obtain approval 1 mon 12 days
Median time taken to obtain approval 1 mon
Minimum time taken to obtain approval 1 day
Maximum time taken to obtain approval 9 mons 28 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate No fee collected

Issue of Completion Certification
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 30
Total number of applications received 337
Total number of applications approved 253
Total number of applications Withdrawn/Returned/Rejected 51
Average time taken to obtain approval 32 days
Median time taken to obtain approval 19 days
Minimum time taken to obtain approval 1 day
Maximum time taken to obtain approval 10 mons 3 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate No fee collected
Change of Land Use Statistics FROM 01.01.2024 TO 31.12.2024
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 120 days
Total No.of application received 1018
No.of G.O issued 439
No.of application withdrawn/rejected/Returned 132
No.of application pending with applicant 132
No.of application sent to Govt. 70
No.of application in DO pending 128
No.of application in HO pending 117
Average time taken to obtain Government Order 212 days
Minimum time taken to obtain Government Order 84 days
Maximum time taken to obtain Government Order 339 days
Average fee taken by the Department for completion of entire process of obtaining Government Order Rs.20,000/-