Building Plan Permission (New/Additional/Revision) - Less than 40,000 SQFT
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 45
Total number of applications received 3726
Total number of applications approved 1392
Total number of applications Withdrawn/Returned/Rejected 1530
Average time taken to obtain approval 1 mon 31 days
Median time taken to obtain approval 1 mon 22 days
Minimum time taken to obtain approval 3 days
Maximum time taken to obtain approval 11 mons 10 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 915,233.00

Building Plan Permission (New/Additional/Revision) - More than 40,000 SQFT
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 90
Total number of applications received 800
Total number of applications approved 277
Total number of applications Withdrawn/Returned/Rejected 190
Average time taken to obtain approval 4 mons 16 days
Median time taken to obtain approval 4 mons 5 days
Minimum time taken to obtain approval 10 days
Maximum time taken to obtain approval 1 year 2 mons 23 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 1,085,654.00

Building Plan Permission (New/Additional/Revision) - High Rise Building
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 120
Total number of applications received 107
Total number of applications approved 25
Total number of applications Withdrawn/Returned/Rejected 21
Average time taken to obtain approval 5 mons 37 days
Median time taken to obtain approval 6 mons 10 days
Minimum time taken to obtain approval 11 days
Maximum time taken to obtain approval 1 year 1 mon 25 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 37,125,104.00

Plinth Inspection
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 15
Total number of applications received 179
Total number of applications approved 63
Total number of applications Withdrawn/Returned/Rejected 25
Average time taken to obtain approval 41 days
Median time taken to obtain approval 1 mon
Minimum time taken to obtain approval 1 day
Maximum time taken to obtain approval 5 mons
Average fee taken by the Department for completion of entire process of obtaining approval/certificate No fee collected

Issue of Completion Certification
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 30
Total number of applications received 155
Total number of applications approved 79
Total number of applications Withdrawn/Returned/Rejected 19
Average time taken to obtain approval 17 days
Median time taken to obtain approval 14 days
Minimum time taken to obtain approval 1 day
Maximum time taken to obtain approval 2 mons 20 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate No fee collected